Construction on the Eastern Busway continues at pace, with more road changes coming over the next few months as the project prepares to finish and connect the new Rā Hihi flyover.
The Reeves Road connection to Aylesbury Street will be open from December 2024 to late January 2025.
In Pakūranga Plaza there will be utility upgrades and car park improvements. Footpaths outside Countdown have been completed and work near Pakūranga Library due to finish soon.
The South Eastern Highway and Tī Rākau Drive will have periodic overnight road layout changes and detours in place
Upgrades of the Mattson Road, William Roberts Road and Tī Rākau Drive intersection continue. The new intersection is due to open in early 2025 and it will enable to traffic to turn into and out of it from all directions.
Access to William Roberts Road from its connecting roads will change in two stages, converting it into two cul-de-sacs in early 2025. William Roberts Road will be accessible from Ayr Road only following the changes.